Excusable Delays: When an Outage or Supplier Failure Excuses Late Performance

Excusable Delays: When an Outage or Supplier Failure Excuses Late Performance

A day-long cloud outage, a supplier that can’t ship, a storm that closes your facility: any of these can make you miss a delivery date on a federal contract. Whether you’re in default or simply late with a valid excuse depends on a short piece of contract language that most small contractors have never read. Every standard contract type has one.

Where the Rule Lives

The wording differs slightly by contract type, but the idea is the same in each. Cost-reimbursement contracts use FAR 52.249-14, titled Excusable Delays. Fixed-price supply and service contracts carry the same concept inside the default clause, FAR 52.249-8. Commercial contracts cover it in paragraph (f) of FAR 52.212-4. Check which clause is in your contract, because that text is what governs. Our overview of government contract types explains which family your contract belongs to.

The Test

A delay is excusable when it arises from a cause that is beyond your control and that happened without your fault or negligence. You have to show both, and you have to show that the event actually caused the delay. The burden is on the contractor.

The clauses list examples: acts of God or of the public enemy, acts of the government in its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes and unusually severe weather. The list is illustrative. An event that isn’t named can still qualify if it meets the test, and an event that is named doesn’t qualify automatically.

Does a Tech Outage Count?

There’s no clean answer, and no published decision yet on the November 2026 outages. A widespread failure at a major cloud provider is plainly beyond a small contractor’s control. The harder questions are fault and causation. Could the work have continued another way? Did you have a reasonable fallback for a dependency you knew was critical? Did the outage really cause the missed date, or were you already behind?

Expect a contracting officer to ask those questions. A contractor who lost one day and can show it was the last day of a schedule that was otherwise on track is in a much stronger position than one who points to the outage to explain a month of slippage.

The Supplier Rule

Failures by subcontractors and suppliers are handled more strictly. Under 52.249-14, a subcontractor’s failure excuses you only if its cause was beyond the control of both of you and without the fault of either. Even then, you aren’t excused if the supplies or services were obtainable from other sources, the contracting officer ordered you in writing to get them elsewhere, and you failed to comply.

In practice that means “our vendor let us down” is not an excuse on its own. You need to show why the vendor failed and that you couldn’t reasonably have obtained the item or service somewhere else in time. Make sure your subcontracts require prompt notice of delays so you can meet your own notice duty. See our guide to flow-down clauses.

Cause Typically excusable? What decides it
Hurricane closes your facility Often Whether the weather was unusually severe for the place and season
Government-directed stop or shutdown Often Documentation of the government act
Major third-party cloud outage Unsettled Foreseeability, fallback options and actual impact
Sole supplier fails to deliver Sometimes Cause of the supplier’s failure and whether alternates existed
Staff shortage or key person quits Rarely Usually treated as within the contractor’s control
Underestimated the work No A business risk the contractor accepted

What You Get: Time, Not Money

An excusable delay protects you from termination for default and entitles you to a revised schedule. It does not pay you for the extra cost. Compensation needs a different basis, such as a change ordered by the government, a government-caused delay, or a stop-work order. Those are covered in our guide to contract modifications and, for funding lapses, in our shutdown survival guide.

Notice: The Step People Miss

The commercial clause is explicit. You must notify the contracting officer in writing as soon as reasonably possible after the delay begins, with the full particulars. You must work to remedy it, and you must give written notice again when it ends. The other clauses are less detailed, but the practical rule is the same: tell the contracting officer early and in writing.

A good notice states what happened and when, which contract requirements are affected, what you are doing to recover, and the new date you expect to meet. Send it even if you think you’ll catch up. A delay raised for the first time after a missed delivery looks like an afterthought.

Protect Your Record

Ask for a bilateral modification that revises the delivery schedule, so the contract itself shows the new date. Without one, a late delivery can still surface in your performance evaluation. If it does, the same documentation supports a rebuttal under the process in our CPARS guide.

Bottom Line

To be excused, a delay has to be beyond your control, not your fault, and the real cause of the slip. Supplier failures face a higher bar. The relief is more time and protection from default, not more money. Give written notice the day the problem starts, and get the schedule change into a modification.