Termination for Convenience: What Small Contractors Can Recover

Termination for Convenience: What Small Contractors Can Recover

The government can end almost any contract at any time when it decides that doing so is in its interest. It doesn’t need you to have done anything wrong. Hundreds of contracts were terminated this way in the past year. A termination for convenience is not a default and it isn’t the end of the money. The contract gives you a right to be paid for what you did, and a process and deadline for claiming it.

Which Clause You Have

What you can recover depends on the termination clause in your contract. Read it before you do anything else.

Contract type Usual clause Basis of recovery
Fixed-price above the simplified acquisition threshold FAR 52.249-2 Costs incurred on the terminated work, a reasonable profit on work done, subcontract settlements and settlement expenses, capped at the contract price
Small fixed-price contracts FAR 52.249-1 (short form) Settled under the same Part 49 principles with simpler procedures
Commercial products and services FAR 52.212-4, paragraph (l) A percentage of the contract price reflecting the percentage of work performed, plus reasonable charges you can show resulted from the termination
Cost-reimbursement FAR 52.249-6 Allowable costs incurred, a portion of the fee and settlement expenses

The First Week

The notice of termination tells you the effective date and how much of the contract is terminated. From that date you must stop work on the terminated portion, place no further orders for it, terminate the related subcontracts, and protect any government property and work in progress. Costs you run up after the effective date by continuing to work are your own.

Start a separate cost code for termination activity immediately and keep time records against it. Those hours are recoverable as settlement expenses only if you can document them, which is one more reason to follow sound timekeeping practices.

What You Can Recover on a Fixed-Price Contract

Completed work. The contract price for items finished and accepted but not yet paid.

Costs incurred. Labor, materials, overhead and other costs reasonably put into the terminated work, including preparation and start-up costs that were to be spread over the full contract.

Profit on work done. A reasonable allowance for profit on the work you performed. If the contract would have lost money had it been completed, profit is not allowed and the settlement is reduced to reflect the loss.

Subcontractor settlements. Reasonable amounts you pay to settle the subcontracts you had to terminate.

Settlement expenses. Accounting, legal and clerical costs of preparing the settlement proposal, and reasonable costs of storing, protecting and disposing of termination inventory.

You can’t recover profit you would have earned on work you never performed. The total, less payments already made, can’t exceed the contract price.

Commercial Contracts Are Different

Under the commercial clause there are no cost principles to apply. You’re paid a percentage of the contract price that matches the percentage of work performed before the notice, plus reasonable charges you can demonstrate resulted from the termination. You show those charges using your standard record-keeping system. The clause doesn’t require you to comply with government cost accounting standards or cost principles for this purpose.

Deadlines That Matter

Under 52.249-2, your final settlement proposal is due no later than one year from the effective date of termination, unless the contracting officer extends it in writing. Miss it and the contracting officer may decide what you’re owed on the information available. Schedules of termination inventory are due within 120 days. If the termination is partial, a request to adjust the price of the continuing work generally must be filed within 90 days.

Don’t wait a year. A small business that needs cash can ask for partial payments against a submitted proposal, which the clause permits. An early, well-supported proposal gets paid faster than a late one.

If You’re a Subcontractor

You have no direct claim against the government. Your recovery runs through the prime, under whatever termination language is in your subcontract. Check that your subcontracts include a termination for convenience clause that mirrors the prime contract, and submit your own settlement proposal to the prime promptly so it can be included in theirs. Our flow-down clause guide explains why this language matters before a termination, not after.

Common Mistakes

Continuing to work after the effective date. Failing to terminate subcontracts and then being billed for work the government won’t pay for. Treating the notice as the end of the matter and never filing. Claiming lost future profit. Having cost records too thin to support the numbers. Most of these come down to accounting, which is where a compliant cost system pays for itself.

If You Can’t Agree

Most settlements are negotiated with a termination contracting officer. If you can’t reach agreement, the contracting officer issues a determination of the amount due. You can challenge it under the contract’s disputes process, which has its own strict deadlines. Terminations during a funding lapse raise extra issues covered in our shutdown survival guide, and changes short of termination are covered in our guide to contract modifications.

Bottom Line

A termination for convenience entitles you to be paid for the work you did, your reasonable costs of stopping, and in most cases a fair profit on performed work. Stop work on the effective date, track termination costs separately, settle with your subcontractors, and file a documented settlement proposal well inside the one-year limit.